TransLink - Petrie to Kippa-Ring public transport corridor study
Skip to primary navigation | Skip to secondary navigation | Skip to content | Skip to Journey Planner |
Problems viewing this site
blue swirlPetrie to Kippa-Ring public transport corridor study





Anzac Avenue noise barriers - construction of noise barriers now complete

The Queensland Government, through the TransLink Transit Authority and Main Roads, has completed installation of the two-kilometre stretch of noise barriers along Anzac Avenue at Rothwell and Kippa-Ring. The noise barriers have been installed to reduce road traffic noise for local residents.


Study background

The Petrie to Kippa-Ring Public Transport Corridor Study (PKPTCS) commenced in November 1999 and investigated the feasibility, preferred development, impacts and benefits of a new public transport corridor between Petrie and Kippa-Ring, north of Brisbane.

In consultation with the local community, the study focused on:
  • Determining the need for a new public transport corridor.
  • Identifying a preferred route for the corridor.
  • Identifying the preferred public transport mode (for example busway, heavy rail, light rail and so on).
  • Identifying station locations.
  • Developing an integrated public transport system.
  • Undertaking impact assessment studies and identifying environmental management strategies.
  • Establishing staging options for the development of public transport infrastructure.




Why did we do the study?

The Regional Framework for Growth Management for south-east Queensland (RFGM), the Integrated Regional Transport Plan and Transport 2007 documents identified the need to investigate a public transport link between Petrie and Kippa-Ring. The Petrie to Kippa-Ring Public Transport Corridor Study aids the achievement of the visions and objectives set out in these documents.




Who undertook the study?

Queensland Transport commissioned consultants, GHD Pty Ltd, to undertake this project on its behalf. The study was undertaken in two stages.




Stage 1 activities

The primary purpose of Stage 1 was to identify the preferred alignment through the Mango Hill/Griffin area and the preferred transport mode. The Mango Hill/Griffin Corridor Options Assessment Report documents the findings of the corridor assessment work undertaken in Stage 1.

What was decided in Stage 1?
It was decided that:
  • Corridor A is the preferred corridor option through the Mango Hill/Griffin area.
  • The preferred transport mode is heavy passenger rail, similar to the current QR network.




Stage 2 activities

Stage 2 of the study commenced in July 2000 and was completed in 2002. Stage 2 primarily involved:
  • Further investigation on the feasibility and impacts of developing the corridor.
  • Refining the preferred route including the best option in the Petrie area.
  • Investigating the staging and timing options.
  • Developing an integrated transport strategy to support the corridor development.
  • Refining station locations.
  • Investigating land use strategies.

As a result of this work, a Final Impact Assessment Study report was produced.

What was decided in Stage 2?
It was decided that:
  • The preferred corridor in the Petrie area is option A, the original preserved corridor.
  • The evaluation and assessment of corridor options through the Petrie area found that the existing corridor (option A) was preferred because:
  • The land is already owned by the state.
  • The alternative option (option D) significantly fragments existing land uses and habitat.
  • Environmental impacts can be managed through mitigation measures.




Community involvement

The community within the study area was involved in the following ways:
  • Freecall information line direct to the study team.
  • Newsletters distributed to all households and businesses in the study area and those on the study mailing list.
    • Newsletter 1 (distributed in December 1999) introduced the study to the community and advised how people could be involved.
    • Newsletter 2 (distributed in July 2000) summarised the outcomes of Stage 1. It also provided advice on the Stage 2 process.
    • Newsletter 3 (distributed in January 2002) summarised the results of the Draft Impact Assessment Study.

Public display of the Draft Impact Assessment Study report and aerial photographs of the study area were available for viewing by the public. Displays were held from 18 December 2001 at local council offices, libraries and Queensland Transport customer service centres until 8 March 2002.

Two community open days were held as part of the consultation process. Staff members from Queensland Transport and GHD were present to answer any questions and ask for community input.
  • The first open day was held on Thursday, 31 January 2002 from 4-8pm at the Redcliffe Entertainment Centre, Downs Street, Redcliffe.
  • The second open day was held on Saturday, 2 February 2002 from 10am-2pm at the Petrie School of Arts, Anzac Avenue, Petrie. Dates, times and venues for these information sessions were also advertised in local newspapers and The Courier-Mail.




What was decided at the end of the study?

Queensland Transport carried out a review of the estimated capital and operating costs contained in the Final Impact Assessment Study (IAS) report. The review revealed the IAS report cost estimates focused on the Petrie to Kippa-Ring corridor only, and did not fully take into consideration the additional costs of operating trains from Kippa-Ring via Petrie to the Brisbane central business district or address the costs of integrating services with the rest of the QR network.

The government considered almost $A 300 million in capital costs for construction of a heavy rail link and the purchase of the rolling stock would place too great a financial burden on Queensland taxpayers. Projections showed that operation of the rail services between Petrie and Kippa-Ring would be a significant annual cost to Queensland taxpayers of about $A 30 million for a limited growth in public transport usage.

In the meantime the ongoing need to protect the preferred Petrie to Kippa-Ring corridor for future public transport purposes has been approved. The timing of the construction of the rail line will be reviewed as part of the Integrated Regional Transport Plan implementation process.




Publications

Released: October 2003

The Petrie to Kippa-Ring Public Transport Corridor Study (PKPTCS) investigated the feasibility, preferred development, impacts and benefits of a new public transport corridor between Petrie and Kippa-Ring, north of Brisbane.

Executive summary of PKPTCS (PDF, 384KB)


Abobe Website
Download Adobe Reader to display and print PDF files. This software is freely distributed by Adobe Systems Inc. While this department has taken every possible precaution with the creation of these files, they are downloaded and used at your own risk. Various tools to enable access to these files for people using screen readers can be found at www.adobe.com/accessibility.


ad
Last updated 16 July 2008

Copyright | Disclaimer | Privacy | Other languages
© TransLink Transit Authority 2008